Stage by stage
| Stage | What happens | Time |
|---|---|---|
| 1. Design | Site visit, type and size, a current survey, a check of your town's pool code | A few weeks, at your pace |
| 2. Plans and extra approvals | Sealed plans where required; Health Department, Trustees or ZBA approvals; utility clearance letter | Varies by town |
| 3. Permit | File with the town, city or village; respond to review comments | 4–6 weeks (published, gunite) |
| 4. Excavation and shell | Temporary fence; dig; steel, plumbing and the shell (gunite cures) | 10–16 weeks for gunite (published) |
| 5. Equipment, tile, coping, finish | Pump, filter, heater; electrical inspection; interior finish | |
| 6. Patio, fence, final | Permanent barrier before water; final inspection and certificate | Varies |
Approvals that add time, by town
- Town of Oyster Bay: plans sealed by an architect or engineer, notarized affidavits from everyone, an installer licensed by Nassau County Consumer Affairs, and a letter confirming 10 feet of clearance from overhead wires.
- Village of Garden City: an engineer- or architect-designed pool and a 6-foot fence screened with evergreens on a landscaping plan approved by the Zoning Board of Appeals.
- Town of North Hempstead: Nassau County Health Department approval first, plus an engineer's drainage certification and a separate fence permit.
- Village of Lindenhurst: no work, even excavation, on an inground pool until the Suffolk County Health Department approves the plans.
- Town of East Hampton: a guaranteed survey and a licensed surveyor's stake-out certification before the permit is issued.
- Town of Southold: a Board of Trustees permit for work within 100 feet of a wetland, beach, bluff or dune.
Deadlines during the build
The Town of Islip and Shelter Island require the permanent barrier within 90 days, a temporary fence must surround the excavation while the pool is built, and most codes bar filling the pool until the barrier is up. In Brookhaven, the pool can't be used until the Building Division issues a certificate of compliance.
Budget alongside the schedule: published Long Island prices run $35,000 – $100,000 for vinyl and $60,000 – $250,000 for gunite. See the price survey, pool permits by town and the best time to start.
Frequently asked questions
How long does it take to build a pool on Long Island?
One Long Island builder publishes 4 to 6 weeks for the permit and 10 to 16 weeks of construction for a gunite pool, including curing. Vinyl and fiberglass pools build faster once the permit is issued. Add design time before the permit and fence, patio and landscaping time after.
What slows a Long Island pool down the most?
Approvals. Sealed plans (Oyster Bay, Garden City), a Health Department approval (North Hempstead, Lindenhurst), a ZBA-approved fence and landscaping plan (Garden City), a surveyor's stake-out (East Hampton) or a Board of Trustees permit near wetlands (Southold) all add steps before digging.
When can I swim in a new pool?
After the permanent barrier is up and the final inspection passes. Most codes bar putting water in a pool until the barrier is in place, and Brookhaven requires a certificate of compliance before an inground pool is used.
Sources
- Long Island pool builder: Levittown gunite page (10–16 week build, 4–6 week permit)
- Town of East Hampton Code § 255-11-89, Swimming pools
- Village of Garden City Code § 200-45, Swimming pools
- Town of North Hempstead Code § 70-102, Outdoor pools
- Village of Lindenhurst Code Ch. 167, Swimming Pools
- Town of Islip Code Art. XXVIII, Swimming Pools (eCode360)
- Town of Brookhaven Code § 85-891, Swimming pools (amended 5-14-2026)
- Town of Oyster Bay pool permit checklist (April 2026)