Why Long Island digs differ so much
Long Island is glacial: a spine of moraine hills (sand, gravel and dense till) with a flat outwash plain of sand and loam running south to the bays. That gives pool builders four very different kinds of ground within a few miles:
- Loam over sand and gravel (Haven, Riverhead, Hempstead soils). The easy case: firm walls, dry holes, good drainage.
- Loose outwash and moraine sand (Plymouth, Carver). It digs fast but won’t hold a vertical wall, so the excavation is sloped back or shored and the backfill compacted in lifts.
- Dense glacial till (Montauk soils). Water perches above the dense layer, so holes fill after rain and dry wells drain slowly.
- South shore fill and wet sand near the bays and canals. Groundwater sits close to the surface, and much of it is in FEMA flood zones.
The 40-town table
Shares of each place’s land, from our grid sample of the USDA soil survey (SSURGO), FEMA’s National Flood Hazard Layer and EPA water-system maps over each Census place boundary (November 2026). “Loose sand” is soil the survey rates excessively drained. These are shares of land, not of homes, so check your own lot on the Web Soil Survey.
| Town | Main soil | 8%+ slopes | Loose sand | Water table within ~3 ft | FEMA flood zone | Watch for |
|---|---|---|---|---|---|---|
| Garden City | Urban land-Hempstead complex | 0% | 4% | 0% | 0% | easy digging |
| Levittown | Urban land-Hempstead complex | 0% | 0% | 6% | 0% | built-over / fill |
| Massapequa | Urban land-Sudbury complex | 0% | 0% | 49% | 21% | groundwater, flood zone, built-over / fill |
| Merrick | Urban land-Sudbury complex | 0% | 4% | 35% | 31% | groundwater, flood zone |
| Rockville Centre | Urban land-Riverhead complex (0–3%) | 0% | 0% | 1% | 1% | built-over / fill |
| Manhasset | Urban land-Montauk complex (3–8%) | 31% | 5% | 62% | 1% | slopes, groundwater |
| Port Washington | Pits, sand and gravel | 13% | 11% | 23% | 5% | easy digging |
| Syosset | Urban land-Hempstead complex | 6% | 2% | 11% | 0% | easy digging |
| Hicksville | Urban land-Hempstead complex | 0% | 0% | 2% | 0% | built-over / fill |
| Huntington | Riverhead–Haven, graded (0–8%) | 36% | 19% | 31% | 1% | slopes, groundwater |
| Northport | Riverhead–Haven, graded (0–8%) | 23% | 20% | 1% | 2% | slopes |
| Dix Hills | Haven loam (0–2%) | 24% | 19% | 25% | 0% | slopes, groundwater |
| Commack | Riverhead–Haven, graded (0–8%) | 8% | 13% | 0% | 0% | easy digging |
| Smithtown | Carver and Plymouth soils (15–35%) | 24% | 46% | 9% | 5% | slopes, loose sand |
| Lindenhurst | Riverhead–Haven, graded (0–8%) | 0% | 1% | 3% | 11% | flood zone, built-over / fill |
| Bay Shore | Riverhead–Haven, graded (0–8%) | 0% | 6% | 2% | 8% | easy digging |
| Southampton | Bridgehampton silt loam (0–2%) | 0% | 8% | 11% | 20% | flood zone |
| Riverhead | Haven loam (0–2%) | 4% | 27% | 7% | 2% | easy digging |
| Stony Brook | Riverhead–Haven, graded (0–8%) | 14% | 26% | 6% | 7% | easy digging |
| Mount Sinai | Haven loam (0–2%) | 19% | 16% | 9% | 9% | easy digging |
| Rocky Point | Riverhead sandy loam (0–3%) | 9% | 23% | 0% | 0% | easy digging |
| Manorville | Carver and Plymouth soils (3–15%) | 15% | 66% | 4% | 2% | loose sand |
| Sayville | Riverhead–Haven, graded (0–8%) | 0% | 13% | 6% | 6% | easy digging |
| East Islip | Riverhead–Haven, graded (0–8%) | 0% | 4% | 9% | 8% | easy digging |
| West Islip | Riverhead–Haven, graded (0–8%) | 0% | 9% | 4% | 7% | easy digging |
| West Babylon | Riverhead–Haven, graded (0–8%) | 0% | 2% | 3% | 8% | easy digging |
| Deer Park | Riverhead–Haven, graded (0–8%) | 0% | 3% | 3% | 0% | easy digging |
| St. James | Riverhead–Haven, graded (0–8%) | 3% | 3% | 1% | 0% | easy digging |
| Kings Park | Riverhead–Haven, graded (0–8%) | 15% | 32% | 4% | 4% | easy digging |
| Nesconset | Haven loam (0–2%) | 7% | 15% | 0% | 0% | easy digging |
| Centerport | Carver and Plymouth soils (15–35%) | 55% | 57% | 3% | 9% | slopes, loose sand |
| Melville | Haven loam (0–2%) | 21% | 21% | 11% | 0% | slopes |
| East Northport | Riverhead–Haven, graded (0–8%) | 14% | 3% | 3% | 0% | easy digging |
| Hampton Bays | Carver and Plymouth soils (3–15%) | 11% | 89% | 6% | 11% | loose sand, flood zone |
| Westhampton | Carver and Plymouth soils (0–3%) | 1% | 63% | 2% | 9% | loose sand |
| Montauk | Montauk loamy sand (15–35%) | 35% | 45% | 59% | 11% | slopes, loose sand, groundwater, flood zone |
| East Hampton | Bridgehampton silt loam (0–2%) | 1% | 33% | 9% | 19% | flood zone |
| Southold | Haven loam (0–2%) | 8% | 26% | 14% | 19% | flood zone |
| Mattituck | Haven loam (0–2%) | 14% | 27% | 6% | 9% | easy digging |
| Shelter Island | Montauk loam (3–8%) | 26% | 31% | 52% | 16% | slopes, groundwater, flood zone |
What each condition adds to the job
- Slopes: a level pad, a retaining wall on the low side, steps, and drainage so runoff doesn’t wash out the deck. A semi-inground pool set into the hill can cut the wall height.
- Loose sand: wider excavation, more backfill, compaction in lifts. Get the backfill method in writing.
- Groundwater: dewatering during the dig and a hydrostatic relief valve, and never draining the pool yourself afterward (liner replacement).
- Flood zones: the town’s flood rules apply on top of the pool code; keep the pump, heater and panel above the flood elevation.
- Built-over or filled ground: a soil check before signing, and compaction under the pool and patio.
The dig, step by step
- Stake-out. The pool is marked from the survey (East Hampton requires a licensed surveyor to stake it before the permit).
- Excavation. For a 16×32 pool, about 100 cubic yards in place, roughly 10 to 12 truckloads once loosened. Access matters: on tight postwar lots, ask how the machine and the trucks get in.
- Walls and plumbing. Steel or polymer panels for vinyl, a shell for fiberglass, steel and shotcrete for gunite.
- The floor. For vinyl pools, a mason or the liner crew trowels a smooth cement-vermiculite or grout floor over the compacted base. If you hired the dig on its own, as some Facebook posters do, line up that floor work before the liner crew is booked.
- Backfill and grade. Compacted around the walls, then graded so the patio and yard drain away from the pool and toward the dry well your town requires (pool drainage and dry wells).
The whole sequence, with permit time, is in the pool installation timeline.
Need it done? Call for inground pool installation on Long Island. Local guides: pools in Massapequa, pools in Manhasset, pools in Nesconset, pools in Centerport, pools in Hampton Bays, pools in Montauk.
Frequently asked questions
How much dirt comes out of a 16×32 inground pool?
About 100 cubic yards in the ground (16 × 32 feet × roughly 5½ feet average depth, including over-dig), which swells to around 125 to 130 cubic yards once loosened: roughly 10 to 12 loads in a 12-yard dump truck. Some is kept for backfill and grading.
Who finishes the bottom of a vinyl liner pool?
A mason or the liner crew troweling a smooth floor, usually a cement-vermiculite or grout mix, over the compacted base before the liner goes in. It's normally part of the pool contract; if a homeowner hired the dig separately, it has to be arranged before the liner crew arrives.
What if the pool dig hits water?
The builder pumps it out (sump pumps or well points) while the floor and walls go in, and the finished pool gets a hydrostatic relief valve. On Shelter Island, the code forbids excavating below the water table at all, which can limit pool depth.
Can a skid steer dig a semi-inground pool?
For a semi-inground pool, often yes, since the dig is shallower. Grade and compaction still matter: the walls and the patio around them need a level, compacted base, and the town permit and fence rules still apply.